Radioactive contamination spreading in shuttered Hanford Site nuclear plant

The Hanford Site plant in Washington hasn’t been operational since 1967, but continues to spread radioactive waste, with a demolition date earmarked as late as 2032.
Although it hasn’t been operational for nearly 50 years, a report published by the Tri-City Herald has found that radioactive contamination is spreading inside the plant’s Reduction-Oxidation Complex (REDOX) and could be worsened as the facility deteriorates.
The facility is roughly half the size of Rhode Island and because REDOX is located so deeply in the center, it poses little risk to the public. However, preventing the problem from worsening isn’t going to be cheap. The report recommends that $148 to $181 million be spent on interim cleanup and maintenance.